Xinjiang 300,000 tons of slag production line has successfully put into operation

11 Sep,2018 UTC+8 Views:


● Raw Material: slag

● Capacity: 300,000 t/a

● Host device : GRMS33.31 slag mill

slag powder line

It is a well known steel production enterprise. On October 24, 2017, it signed a contract with chaeng for the annual production of 300,000 tons of slag powder production line project. The project was officially launched on December 17, 2017 and it successfully put into operation in April 2018.

Operation situation

slag powder line

300,000 t/a slag powder production line project is operated by load, the output is 45t/h, the specific surface area is ≥400m2/kg, and the output and quality meet the design requirements.

Project display

slag grinding plant

slag grinding millslag grinding mill

 

Chaeng can provide EPC general contracting services for single line production of 10-1.5 million tons of slag production line. Up to now, chaeng has successfully established 110 slag powder production lines at home and abroad.